Project Start Date: Mon 01-12-17
Project Finish Date: Mon 02-06-17

Brunel_Planning

IDWBS
Name
ResponsibleDurationStart_DatePlanned_Finish_DateActual_Finish_DatePredecessors
11.1
Event Data Model
 77 days?Mon 01-12-17Tue 02-04-02NA 
21.1
Reviews
 70 daysMon 01-12-17Mon 02-03-25Mon 02-03-25 
31.1.1
Container Classes
M.Frank0 daysMon 01-12-17Mon 01-12-17Mon 01-12-17 
41.1.2
Top Level
M.Cattaneo0 daysMon 02-03-04Mon 02-03-04Mon 02-03-04 
51.1.3
MCEvent
G.Corti0 daysMon 02-03-04Mon 02-03-04Mon 02-03-04 
61.1.4
L0
 41 daysMon 02-01-14Tue 02-03-12Tue 02-03-12 
71.1.4.1
L0Calo
O.Callot0 daysMon 02-01-14Mon 02-01-14Mon 02-01-14 
81.1.4.2
L0Muon
A.Tsaregorodtsev0 daysTue 02-03-12Tue 02-03-12Tue 02-03-12 
91.1.4.3
L0PuVeto
O.Callot0 daysMon 02-01-14Mon 02-01-14Mon 02-01-14 
101.1.4.4
L0DU
O.Callot0 daysMon 02-01-14Mon 02-01-14Mon 02-01-14 
111.1.5
L1
O.Callot0 daysMon 02-03-25Mon 02-03-25Mon 02-03-25 
121.1.6
VELO
C.Parkes0 daysMon 02-01-14Mon 02-01-14Mon 02-01-14 
131.1.7
IT
M.Needham0 daysMon 02-01-28Mon 02-01-28Mon 02-01-28 
141.1.8
OT
J.v.Tilburg0 daysMon 02-01-28Mon 02-01-28Mon 02-01-28 
151.1.9
Tracking
J.v.Tilburg0 daysMon 02-01-28Mon 02-01-28Mon 02-01-28 
161.1.10
RICH
 0 daysMon 02-02-04Mon 02-02-04Mon 02-02-04 
171.1.10.1
Simulation
A.Presland0 daysMon 02-02-04Mon 02-02-04Mon 02-02-04 
181.1.10.2
PID
C.Jones0 daysMon 02-02-04Mon 02-02-04Mon 02-02-04 
191.1.11
CALO
V.Belyaev0 daysMon 02-02-18Mon 02-02-18Mon 02-02-18 
201.1.12
MUON
 21 daysMon 02-02-11Tue 02-03-12Tue 02-03-12 
211.1.12.1
Digitisation
A.Satta0 daysMon 02-02-11Mon 02-02-11Mon 02-02-11 
221.1.12.2
PID
D.Hutchcroft0 daysTue 02-03-12Tue 02-03-12Tue 02-03-12 
231.1.13
Physics
G.Corti0 daysMon 02-01-21Mon 02-01-21Mon 02-01-21 
241.1.14
Reference Tables
V.Belyaev0 daysMon 02-02-11Mon 02-02-11Mon 02-02-11 
251.2
Implementation
 77 days?Mon 01-12-17Tue 02-04-02NA 
261.2.1
Container Classes
M.Frank37 daysMon 01-12-17Tue 02-02-05Tue 02-02-053
271.2.2
Top Level
M.Cattaneo12 daysMon 02-03-04Tue 02-03-19Tue 02-03-194
281.2.3
MCEvent
G.Corti12 daysMon 02-03-04Tue 02-03-19Tue 02-03-195
291.2.4
L0
 46 daysMon 02-01-14Mon 02-03-18NA 
301.2.4.1
L0Calo
O.Callot13 daysMon 02-01-14Wed 02-01-30Wed 02-01-307
311.2.4.2
L0Muon
A.Tsaregorodtsev5 daysTue 02-03-12Mon 02-03-18NA8
321.2.4.3
L0PuVeto
O.Callot13 daysMon 02-01-14Wed 02-01-30Wed 02-01-309
331.2.4.4
L0DU
O.Callot13 daysMon 02-01-14Wed 02-01-30Wed 02-01-3010
341.2.5
L1
O.Callot5 daysMon 02-03-25Fri 02-03-29NA11
351.2.6
VELO
C.Parkes57 daysMon 02-01-14Tue 02-04-02NA12
361.2.7
IT
M.Needham31 days?Mon 02-01-28Mon 02-03-11NA13
371.2.8
OT
J.v.Tilburg31 days?Mon 02-01-28Mon 02-03-11NA14
381.2.9
Tracking
J.v.Tilburg36 daysMon 02-01-28Mon 02-03-18NA15
391.2.10
RICH
 36 daysMon 02-02-04Mon 02-03-25NA 
401.2.10.1
Simulation
A.Presland36 daysMon 02-02-04Mon 02-03-25NA17
411.2.10.2
PID
C.Jones36 daysMon 02-02-04Mon 02-03-25NA18
421.2.11
CALO
V.Belyaev27 daysMon 02-02-18Tue 02-03-26Tue 02-03-2619
431.2.12
MUON
 23 days?Mon 02-02-11Wed 02-03-13NA 
441.2.12.1
Digitisation
A.Satta16 daysMon 02-02-11Mon 02-03-04NA21
451.2.12.2
PID
D.Hutchcroft2 days?Tue 02-03-12Wed 02-03-13NA22
461.2.13
ProtoParticles
G.Corti5 daysWed 02-03-27Tue 02-04-02NA38,41,42,45
471.2.14
Physics
G.Corti41 daysMon 02-01-21Mon 02-03-18NA23
481.2.15
Reference Tables
V.Belyaev21 daysMon 02-02-11Mon 02-03-11NA24
49        
502
Algorithms for new model
 63 days?Wed 02-01-30Mon 02-04-29NA26
512.1
L0
 59 days?Wed 02-01-30Tue 02-04-23NA 
522.1.1
L0Calo Simulation
O.Callot0 days?Wed 02-01-30Wed 02-01-30Wed 02-01-3030
532.1.2
L0Muon Simulation
A.Tsaregorodtsev1 day?Tue 02-03-19Tue 02-03-19NA31
542.1.3
L0PuVeto Simulation
O.Callot2 daysMon 02-04-22Tue 02-04-23NA32,35,63FF
552.1.4
L0DU Simulation
P.Perret0 days?Wed 02-01-30Wed 02-01-30Wed 02-01-3033
562.2
L1
O.Callot21 daysMon 02-04-01Mon 02-04-29NA34
572.2.1
2D+3D tracks and vertices
I.Kisel10 daysWed 02-04-10Tue 02-04-23NA63FF
582.2.2
L1Track to L0 Candidate Matching
N.Tuning20 daysMon 02-04-01Fri 02-04-26NA57FF
592.2.3
L1 matching to TT1
M.Witek10 daysWed 02-04-10Tue 02-04-23NA57FF
602.2.4
L1 Decision (Super L1 FortranNN
N.Tuning1 dayMon 02-04-29Mon 02-04-29NA58
612.3
Velo
C.Parkes15 daysWed 02-04-03Tue 02-04-23NA35
622.3.1
Velo RAWH converter
J.Palacios1 dayWed 02-04-03Wed 02-04-03NA 
632.3.2
Velo Silicon Simulation
 15 daysWed 02-04-03Tue 02-04-23NA62FF
642.3.3
Velo Clustering
 15 daysWed 02-04-03Tue 02-04-23NA63FF
652.4
IT
M.Needham16 days?Tue 02-03-12Tue 02-04-02NA36
662.4.1
IT RAWH converter
 1 day?Tue 02-03-12Tue 02-03-12NA 
672.4.2
IT Digitisation and Clustering
 16 daysTue 02-03-12Tue 02-04-02NA98FF
682.5
OT
J.v.Tilburg15 days?Tue 02-03-12Mon 02-04-01NA37
692.5.1
OT RAWH converter
 1 day?Tue 02-03-12Tue 02-03-12NA 
702.5.2
OT Digitisation and clustering
 15 daysTue 02-03-12Mon 02-04-01NA 
712.6
Tracking
M.Merk26 days?Tue 02-03-19Tue 02-04-23NA38
722.6.1
Stub seeding
R.Forty,R.Hierck5 daysWed 02-03-27Tue 02-04-02NA65FF,68FF
732.6.2
Fast seeding
B.Hommels5 daysWed 02-03-27Tue 02-04-02NA65FF,68FF
742.6.3
Velo Tracking
F.Teubert10 daysWed 02-04-10Tue 02-04-23NA61FF
752.6.4
Track Matching
J.v.Tilburg5 daysWed 02-04-17Tue 02-04-23NA72FF,74FF
762.6.5
Track Following
R.Hierck10 daysWed 02-04-10Tue 02-04-23NA72FF,61FF
772.6.6
Forward Tracking
O.Callot5 daysWed 02-04-17Tue 02-04-23NA74FF,65FF,68FF
782.6.7
Track Fit
O.Callot,J.v.Tilburg20 daysTue 02-03-19Mon 02-04-15NA65FF,68FF
792.6.8
Track Selection ("clone killer")
 1 day?Tue 02-04-23Tue 02-04-23NA75FF,76FF,77FF,72FF,78FF
802.6.9
Back Converter to AXAT
C.Jones1 day?Tue 02-03-19Tue 02-03-19NA 
812.7
RICH
 11 daysMon 02-03-11Mon 02-03-25NA 
822.7.1
Remove ATMC references
G.Wilkinson5 daysMon 02-03-11Fri 02-03-15NA 
832.7.2
Converters SICB to RichEvent
C.Jones10 daysTue 02-03-12Mon 02-03-25NA39FF
842.8
CALO
V.Belyaev1 day?Wed 02-03-27Wed 02-03-27NA42
852.8.1
Digitisation and Reconstruction
 1 day?Wed 02-03-27Wed 02-03-27NA 
862.8.2
CaloParticle creator
 1 day?Wed 02-03-27Wed 02-03-27NA 
872.9
Muon
D.Hutchcroft29 days?Thu 02-03-14Tue 02-04-23NA43
882.9.1
Muon RAWH converter
D.Hutchcroft1 day?Thu 02-03-14Thu 02-03-14NA 
892.9.2
Muon Digitisation
A.Satta14 daysThu 02-03-14Tue 02-04-02NA88FF
902.9.3
Muon Reconstruction
D.Hutchcroft1 day?Tue 02-04-02Tue 02-04-02NA89FF
912.9.4
Muon PID
Joao22 daysMon 02-03-25Tue 02-04-23NA90FF,79FF
922.9.5
Muon background
 15 daysWed 02-04-03Tue 02-04-23NA89
932.10
Common
 31 days?Tue 02-03-12Tue 02-04-23NA 
942.10.1
Top Level RAWH converters
M.Cattaneo5 days?Wed 02-03-20Tue 02-03-26Tue 02-03-2627
952.10.2
MCEvent RAWH converters
M.Cattaneo5 days?Wed 02-03-20Tue 02-03-26Tue 02-03-2628
962.10.3
Primary Vertex reconstruction
M.Witek31 daysTue 02-03-12Tue 02-04-23NA74FF,79FF
972.10.4
ProtoParticles creator
G.Corti10 daysWed 02-04-03Tue 02-04-16NA46
982.10.5
Association tool example and interface
P.Charpentier5 daysThu 02-03-14Wed 02-03-20NA48FF
99        
1003
OO-DST prototype
 19 days?Wed 02-04-03Mon 02-04-29NA25
1013.1
Definition of content
 2 days?Wed 02-04-03Thu 02-04-04NA1
1023.1.1
Event Model Classes
M.Cattaneo1 day?Wed 02-04-03Wed 02-04-03NA 
1033.1.2
Relationship classes
M.Cattaneo1 day?Thu 02-04-04Thu 02-04-04NA102
1043.2
Association tools
 1 day?Fri 02-04-05Fri 02-04-05NA103
1053.3
Prototype interface to book-keeping
 1 day?Wed 02-04-03Wed 02-04-03NA 
1063.4
Produce 10 events for protoparticle development
M.Cattaneo0 days?Mon 02-04-29Mon 02-04-29NA101,50
107        
1084
OO-DST prototype ready
 0 daysTue 02-04-30Tue 02-04-30NA1,50,100
109        
1105
XML geometry and tools
 119 days?Mon 01-12-17Fri 02-05-31NA 
1115.1
LHCb-Light geometry defined
 0 daysFri 02-05-31Fri 02-05-31NA 
1125.2
Infrastructure
 119 daysMon 01-12-17Fri 02-05-31NA 
1135.2.1
Beam pipe
G.Pakhlova5 daysFri 02-05-24Fri 02-05-31NA111FF
1145.2.2
Velo exit window
 10 daysMon 01-12-17Fri 01-12-28NA 
1155.3
VELO
J.Palacios10 daysFri 02-05-17Fri 02-05-31NA111FF
1165.4
IT
Zurich?15 daysFri 02-05-10Fri 02-05-31NA111FF
1175.5
OT
Nikhef?15 daysFri 02-05-10Fri 02-05-31NA111FF
1185.6
RICH
 64 daysMon 02-03-04Fri 02-05-31NA 
1195.6.1
RICH1
S.Easo10 daysFri 02-05-17Fri 02-05-31NA111FF
1205.6.2
RICH2
A.Papanestis20 daysMon 02-03-04Fri 02-03-29NA 
1215.7
CALO
 1 day?Mon 02-02-25Mon 02-02-25Mon 02-02-25 
1225.7.1
ECAL
G.Pakhlova1 day?Mon 02-02-25Mon 02-02-25Mon 02-02-25 
1235.7.2
HCAL
A.Berdyugin1 day?Mon 02-02-25Mon 02-02-25Mon 02-02-25 
1245.8
MUON
D.Hutchcroft51 days?Mon 01-12-17Mon 02-02-25Mon 02-02-25 
1255.9
Magnetic field service
 1 day?Mon 01-12-17Mon 01-12-17NA 
1265.10
Particle swimmer
 10 daysFri 02-05-17Fri 02-05-31NA112FF,115FF,116FF,117FF,118FF,125FF
127        
1286
Commission algorithms (new geometry etc.)
 56 days?Thu 02-03-28Thu 02-06-13NA 
1296.1
L0PuVeto
Nikhef1 day?Fri 02-05-31Fri 02-05-31NA115
1306.2
VELO
C.Parkes1 day?Fri 02-05-31Fri 02-05-31NA115,61
1316.3
IT
M.Needham1 day?Fri 02-05-31Fri 02-05-31NA116,65
1326.4
OT
J.v.Tilburg1 day?Fri 02-05-31Fri 02-05-31NA117,68
1336.5
Tracking
 1 day?Mon 02-06-03Mon 02-06-03NA130,131,132,71
1346.6
RICH
 37 daysWed 02-04-24Thu 02-06-13NA 
1356.6.1
Tuning to new tracks
G.Wilkinson15 daysWed 02-04-24Tue 02-05-14NA79
1366.6.2
Tuning to new geometry
G.Wilkinson10 daysFri 02-05-31Thu 02-06-13NA118,133FF,81
1376.7
CALO
V.Belyaev1 day?Thu 02-03-28Thu 02-03-28NA121,84
1386.8
MUON
D.Hutchcroft1 day?Wed 02-04-24Wed 02-04-24NA124,87
139        
1407
Commission OO-DSTs
 33 daysWed 02-05-01Fri 02-06-14NA108
1417.1
RAW (digi output)
 28 daysWed 02-05-01Fri 02-06-07NA 
1427.1.1
Finalise content
M.Cattaneo5 daysWed 02-05-01Tue 02-05-07NA 
1437.1.2
Commission Brunel Digi
M.Cattaneo5 daysMon 02-06-03Fri 02-06-07NA130,131,132,137,138,142,129
1447.2
EOD (reco output)
 33 daysWed 02-05-01Fri 02-06-14NA 
1457.2.1
Finalise content
M.Cattaneo5 daysWed 02-05-01Tue 02-05-07NA 
1467.2.2
Back converters for RICH reco
C.Jones10 daysWed 02-05-01Tue 02-05-14NA 
1477.2.3
Test content with physics analysis
G.Corti10 daysWed 02-05-15Tue 02-05-28NA146,145
1487.2.4
Commission Brunel Reco
M.Cattaneo5 daysMon 02-06-10Fri 02-06-14NA143,147,128FF
149        
1508
Release Brunel v10r0
M.Cattaneo0 daysMon 02-06-17Mon 02-06-17NA110,128,140