Project Start Date: Mon 01-12-17
Project Finish Date: Mon 02-06-17
| ID | WBS | Name | Responsible | Duration | Start_Date | Planned_Finish_Date | Actual_Finish_Date | Predecessors |
|---|---|---|---|---|---|---|---|---|
| 1 | 1.1 | Event Data Model | 77 days? | Mon 01-12-17 | Tue 02-04-02 | NA | ||
| 2 | 1.1 | Reviews | 70 days | Mon 01-12-17 | Mon 02-03-25 | Mon 02-03-25 | ||
| 3 | 1.1.1 | Container Classes | M.Frank | 0 days | Mon 01-12-17 | Mon 01-12-17 | Mon 01-12-17 | |
| 4 | 1.1.2 | Top Level | M.Cattaneo | 0 days | Mon 02-03-04 | Mon 02-03-04 | Mon 02-03-04 | |
| 5 | 1.1.3 | MCEvent | G.Corti | 0 days | Mon 02-03-04 | Mon 02-03-04 | Mon 02-03-04 | |
| 6 | 1.1.4 | L0 | 41 days | Mon 02-01-14 | Tue 02-03-12 | Tue 02-03-12 | ||
| 7 | 1.1.4.1 | L0Calo | O.Callot | 0 days | Mon 02-01-14 | Mon 02-01-14 | Mon 02-01-14 | |
| 8 | 1.1.4.2 | L0Muon | A.Tsaregorodtsev | 0 days | Tue 02-03-12 | Tue 02-03-12 | Tue 02-03-12 | |
| 9 | 1.1.4.3 | L0PuVeto | O.Callot | 0 days | Mon 02-01-14 | Mon 02-01-14 | Mon 02-01-14 | |
| 10 | 1.1.4.4 | L0DU | O.Callot | 0 days | Mon 02-01-14 | Mon 02-01-14 | Mon 02-01-14 | |
| 11 | 1.1.5 | L1 | O.Callot | 0 days | Mon 02-03-25 | Mon 02-03-25 | Mon 02-03-25 | |
| 12 | 1.1.6 | VELO | C.Parkes | 0 days | Mon 02-01-14 | Mon 02-01-14 | Mon 02-01-14 | |
| 13 | 1.1.7 | IT | M.Needham | 0 days | Mon 02-01-28 | Mon 02-01-28 | Mon 02-01-28 | |
| 14 | 1.1.8 | OT | J.v.Tilburg | 0 days | Mon 02-01-28 | Mon 02-01-28 | Mon 02-01-28 | |
| 15 | 1.1.9 | Tracking | J.v.Tilburg | 0 days | Mon 02-01-28 | Mon 02-01-28 | Mon 02-01-28 | |
| 16 | 1.1.10 | RICH | 0 days | Mon 02-02-04 | Mon 02-02-04 | Mon 02-02-04 | ||
| 17 | 1.1.10.1 | Simulation | A.Presland | 0 days | Mon 02-02-04 | Mon 02-02-04 | Mon 02-02-04 | |
| 18 | 1.1.10.2 | PID | C.Jones | 0 days | Mon 02-02-04 | Mon 02-02-04 | Mon 02-02-04 | |
| 19 | 1.1.11 | CALO | V.Belyaev | 0 days | Mon 02-02-18 | Mon 02-02-18 | Mon 02-02-18 | |
| 20 | 1.1.12 | MUON | 21 days | Mon 02-02-11 | Tue 02-03-12 | Tue 02-03-12 | ||
| 21 | 1.1.12.1 | Digitisation | A.Satta | 0 days | Mon 02-02-11 | Mon 02-02-11 | Mon 02-02-11 | |
| 22 | 1.1.12.2 | PID | D.Hutchcroft | 0 days | Tue 02-03-12 | Tue 02-03-12 | Tue 02-03-12 | |
| 23 | 1.1.13 | Physics | G.Corti | 0 days | Mon 02-01-21 | Mon 02-01-21 | Mon 02-01-21 | |
| 24 | 1.1.14 | Reference Tables | V.Belyaev | 0 days | Mon 02-02-11 | Mon 02-02-11 | Mon 02-02-11 | |
| 25 | 1.2 | Implementation | 77 days? | Mon 01-12-17 | Tue 02-04-02 | NA | ||
| 26 | 1.2.1 | Container Classes | M.Frank | 37 days | Mon 01-12-17 | Tue 02-02-05 | Tue 02-02-05 | 3 |
| 27 | 1.2.2 | Top Level | M.Cattaneo | 12 days | Mon 02-03-04 | Tue 02-03-19 | Tue 02-03-19 | 4 |
| 28 | 1.2.3 | MCEvent | G.Corti | 12 days | Mon 02-03-04 | Tue 02-03-19 | Tue 02-03-19 | 5 |
| 29 | 1.2.4 | L0 | 46 days | Mon 02-01-14 | Mon 02-03-18 | NA | ||
| 30 | 1.2.4.1 | L0Calo | O.Callot | 13 days | Mon 02-01-14 | Wed 02-01-30 | Wed 02-01-30 | 7 |
| 31 | 1.2.4.2 | L0Muon | A.Tsaregorodtsev | 5 days | Tue 02-03-12 | Mon 02-03-18 | NA | 8 |
| 32 | 1.2.4.3 | L0PuVeto | O.Callot | 13 days | Mon 02-01-14 | Wed 02-01-30 | Wed 02-01-30 | 9 |
| 33 | 1.2.4.4 | L0DU | O.Callot | 13 days | Mon 02-01-14 | Wed 02-01-30 | Wed 02-01-30 | 10 |
| 34 | 1.2.5 | L1 | O.Callot | 5 days | Mon 02-03-25 | Fri 02-03-29 | NA | 11 |
| 35 | 1.2.6 | VELO | C.Parkes | 57 days | Mon 02-01-14 | Tue 02-04-02 | NA | 12 |
| 36 | 1.2.7 | IT | M.Needham | 31 days? | Mon 02-01-28 | Mon 02-03-11 | NA | 13 |
| 37 | 1.2.8 | OT | J.v.Tilburg | 31 days? | Mon 02-01-28 | Mon 02-03-11 | NA | 14 |
| 38 | 1.2.9 | Tracking | J.v.Tilburg | 36 days | Mon 02-01-28 | Mon 02-03-18 | NA | 15 |
| 39 | 1.2.10 | RICH | 36 days | Mon 02-02-04 | Mon 02-03-25 | NA | ||
| 40 | 1.2.10.1 | Simulation | A.Presland | 36 days | Mon 02-02-04 | Mon 02-03-25 | NA | 17 |
| 41 | 1.2.10.2 | PID | C.Jones | 36 days | Mon 02-02-04 | Mon 02-03-25 | NA | 18 |
| 42 | 1.2.11 | CALO | V.Belyaev | 27 days | Mon 02-02-18 | Tue 02-03-26 | Tue 02-03-26 | 19 |
| 43 | 1.2.12 | MUON | 23 days? | Mon 02-02-11 | Wed 02-03-13 | NA | ||
| 44 | 1.2.12.1 | Digitisation | A.Satta | 16 days | Mon 02-02-11 | Mon 02-03-04 | NA | 21 |
| 45 | 1.2.12.2 | PID | D.Hutchcroft | 2 days? | Tue 02-03-12 | Wed 02-03-13 | NA | 22 |
| 46 | 1.2.13 | ProtoParticles | G.Corti | 5 days | Wed 02-03-27 | Tue 02-04-02 | NA | 38,41,42,45 |
| 47 | 1.2.14 | Physics | G.Corti | 41 days | Mon 02-01-21 | Mon 02-03-18 | NA | 23 |
| 48 | 1.2.15 | Reference Tables | V.Belyaev | 21 days | Mon 02-02-11 | Mon 02-03-11 | NA | 24 |
| 49 | ||||||||
| 50 | 2 | Algorithms for new model | 63 days? | Wed 02-01-30 | Mon 02-04-29 | NA | 26 | |
| 51 | 2.1 | L0 | 59 days? | Wed 02-01-30 | Tue 02-04-23 | NA | ||
| 52 | 2.1.1 | L0Calo Simulation | O.Callot | 0 days? | Wed 02-01-30 | Wed 02-01-30 | Wed 02-01-30 | 30 |
| 53 | 2.1.2 | L0Muon Simulation | A.Tsaregorodtsev | 1 day? | Tue 02-03-19 | Tue 02-03-19 | NA | 31 |
| 54 | 2.1.3 | L0PuVeto Simulation | O.Callot | 2 days | Mon 02-04-22 | Tue 02-04-23 | NA | 32,35,63FF |
| 55 | 2.1.4 | L0DU Simulation | P.Perret | 0 days? | Wed 02-01-30 | Wed 02-01-30 | Wed 02-01-30 | 33 |
| 56 | 2.2 | L1 | O.Callot | 21 days | Mon 02-04-01 | Mon 02-04-29 | NA | 34 |
| 57 | 2.2.1 | 2D+3D tracks and vertices | I.Kisel | 10 days | Wed 02-04-10 | Tue 02-04-23 | NA | 63FF |
| 58 | 2.2.2 | L1Track to L0 Candidate Matching | N.Tuning | 20 days | Mon 02-04-01 | Fri 02-04-26 | NA | 57FF |
| 59 | 2.2.3 | L1 matching to TT1 | M.Witek | 10 days | Wed 02-04-10 | Tue 02-04-23 | NA | 57FF |
| 60 | 2.2.4 | L1 Decision (Super L1 FortranNN | N.Tuning | 1 day | Mon 02-04-29 | Mon 02-04-29 | NA | 58 |
| 61 | 2.3 | Velo | C.Parkes | 15 days | Wed 02-04-03 | Tue 02-04-23 | NA | 35 |
| 62 | 2.3.1 | Velo RAWH converter | J.Palacios | 1 day | Wed 02-04-03 | Wed 02-04-03 | NA | |
| 63 | 2.3.2 | Velo Silicon Simulation | 15 days | Wed 02-04-03 | Tue 02-04-23 | NA | 62FF | |
| 64 | 2.3.3 | Velo Clustering | 15 days | Wed 02-04-03 | Tue 02-04-23 | NA | 63FF | |
| 65 | 2.4 | IT | M.Needham | 16 days? | Tue 02-03-12 | Tue 02-04-02 | NA | 36 |
| 66 | 2.4.1 | IT RAWH converter | 1 day? | Tue 02-03-12 | Tue 02-03-12 | NA | ||
| 67 | 2.4.2 | IT Digitisation and Clustering | 16 days | Tue 02-03-12 | Tue 02-04-02 | NA | 98FF | |
| 68 | 2.5 | OT | J.v.Tilburg | 15 days? | Tue 02-03-12 | Mon 02-04-01 | NA | 37 |
| 69 | 2.5.1 | OT RAWH converter | 1 day? | Tue 02-03-12 | Tue 02-03-12 | NA | ||
| 70 | 2.5.2 | OT Digitisation and clustering | 15 days | Tue 02-03-12 | Mon 02-04-01 | NA | ||
| 71 | 2.6 | Tracking | M.Merk | 26 days? | Tue 02-03-19 | Tue 02-04-23 | NA | 38 |
| 72 | 2.6.1 | Stub seeding | R.Forty,R.Hierck | 5 days | Wed 02-03-27 | Tue 02-04-02 | NA | 65FF,68FF |
| 73 | 2.6.2 | Fast seeding | B.Hommels | 5 days | Wed 02-03-27 | Tue 02-04-02 | NA | 65FF,68FF |
| 74 | 2.6.3 | Velo Tracking | F.Teubert | 10 days | Wed 02-04-10 | Tue 02-04-23 | NA | 61FF |
| 75 | 2.6.4 | Track Matching | J.v.Tilburg | 5 days | Wed 02-04-17 | Tue 02-04-23 | NA | 72FF,74FF |
| 76 | 2.6.5 | Track Following | R.Hierck | 10 days | Wed 02-04-10 | Tue 02-04-23 | NA | 72FF,61FF |
| 77 | 2.6.6 | Forward Tracking | O.Callot | 5 days | Wed 02-04-17 | Tue 02-04-23 | NA | 74FF,65FF,68FF |
| 78 | 2.6.7 | Track Fit | O.Callot,J.v.Tilburg | 20 days | Tue 02-03-19 | Mon 02-04-15 | NA | 65FF,68FF |
| 79 | 2.6.8 | Track Selection ("clone killer") | 1 day? | Tue 02-04-23 | Tue 02-04-23 | NA | 75FF,76FF,77FF,72FF,78FF | |
| 80 | 2.6.9 | Back Converter to AXAT | C.Jones | 1 day? | Tue 02-03-19 | Tue 02-03-19 | NA | |
| 81 | 2.7 | RICH | 11 days | Mon 02-03-11 | Mon 02-03-25 | NA | ||
| 82 | 2.7.1 | Remove ATMC references | G.Wilkinson | 5 days | Mon 02-03-11 | Fri 02-03-15 | NA | |
| 83 | 2.7.2 | Converters SICB to RichEvent | C.Jones | 10 days | Tue 02-03-12 | Mon 02-03-25 | NA | 39FF |
| 84 | 2.8 | CALO | V.Belyaev | 1 day? | Wed 02-03-27 | Wed 02-03-27 | NA | 42 |
| 85 | 2.8.1 | Digitisation and Reconstruction | 1 day? | Wed 02-03-27 | Wed 02-03-27 | NA | ||
| 86 | 2.8.2 | CaloParticle creator | 1 day? | Wed 02-03-27 | Wed 02-03-27 | NA | ||
| 87 | 2.9 | Muon | D.Hutchcroft | 29 days? | Thu 02-03-14 | Tue 02-04-23 | NA | 43 |
| 88 | 2.9.1 | Muon RAWH converter | D.Hutchcroft | 1 day? | Thu 02-03-14 | Thu 02-03-14 | NA | |
| 89 | 2.9.2 | Muon Digitisation | A.Satta | 14 days | Thu 02-03-14 | Tue 02-04-02 | NA | 88FF |
| 90 | 2.9.3 | Muon Reconstruction | D.Hutchcroft | 1 day? | Tue 02-04-02 | Tue 02-04-02 | NA | 89FF |
| 91 | 2.9.4 | Muon PID | Joao | 22 days | Mon 02-03-25 | Tue 02-04-23 | NA | 90FF,79FF |
| 92 | 2.9.5 | Muon background | 15 days | Wed 02-04-03 | Tue 02-04-23 | NA | 89 | |
| 93 | 2.10 | Common | 31 days? | Tue 02-03-12 | Tue 02-04-23 | NA | ||
| 94 | 2.10.1 | Top Level RAWH converters | M.Cattaneo | 5 days? | Wed 02-03-20 | Tue 02-03-26 | Tue 02-03-26 | 27 |
| 95 | 2.10.2 | MCEvent RAWH converters | M.Cattaneo | 5 days? | Wed 02-03-20 | Tue 02-03-26 | Tue 02-03-26 | 28 |
| 96 | 2.10.3 | Primary Vertex reconstruction | M.Witek | 31 days | Tue 02-03-12 | Tue 02-04-23 | NA | 74FF,79FF |
| 97 | 2.10.4 | ProtoParticles creator | G.Corti | 10 days | Wed 02-04-03 | Tue 02-04-16 | NA | 46 |
| 98 | 2.10.5 | Association tool example and interface | P.Charpentier | 5 days | Thu 02-03-14 | Wed 02-03-20 | NA | 48FF |
| 99 | ||||||||
| 100 | 3 | OO-DST prototype | 19 days? | Wed 02-04-03 | Mon 02-04-29 | NA | 25 | |
| 101 | 3.1 | Definition of content | 2 days? | Wed 02-04-03 | Thu 02-04-04 | NA | 1 | |
| 102 | 3.1.1 | Event Model Classes | M.Cattaneo | 1 day? | Wed 02-04-03 | Wed 02-04-03 | NA | |
| 103 | 3.1.2 | Relationship classes | M.Cattaneo | 1 day? | Thu 02-04-04 | Thu 02-04-04 | NA | 102 |
| 104 | 3.2 | Association tools | 1 day? | Fri 02-04-05 | Fri 02-04-05 | NA | 103 | |
| 105 | 3.3 | Prototype interface to book-keeping | 1 day? | Wed 02-04-03 | Wed 02-04-03 | NA | ||
| 106 | 3.4 | Produce 10 events for protoparticle development | M.Cattaneo | 0 days? | Mon 02-04-29 | Mon 02-04-29 | NA | 101,50 |
| 107 | ||||||||
| 108 | 4 | OO-DST prototype ready | 0 days | Tue 02-04-30 | Tue 02-04-30 | NA | 1,50,100 | |
| 109 | ||||||||
| 110 | 5 | XML geometry and tools | 119 days? | Mon 01-12-17 | Fri 02-05-31 | NA | ||
| 111 | 5.1 | LHCb-Light geometry defined | 0 days | Fri 02-05-31 | Fri 02-05-31 | NA | ||
| 112 | 5.2 | Infrastructure | 119 days | Mon 01-12-17 | Fri 02-05-31 | NA | ||
| 113 | 5.2.1 | Beam pipe | G.Pakhlova | 5 days | Fri 02-05-24 | Fri 02-05-31 | NA | 111FF |
| 114 | 5.2.2 | Velo exit window | 10 days | Mon 01-12-17 | Fri 01-12-28 | NA | ||
| 115 | 5.3 | VELO | J.Palacios | 10 days | Fri 02-05-17 | Fri 02-05-31 | NA | 111FF |
| 116 | 5.4 | IT | Zurich? | 15 days | Fri 02-05-10 | Fri 02-05-31 | NA | 111FF |
| 117 | 5.5 | OT | Nikhef? | 15 days | Fri 02-05-10 | Fri 02-05-31 | NA | 111FF |
| 118 | 5.6 | RICH | 64 days | Mon 02-03-04 | Fri 02-05-31 | NA | ||
| 119 | 5.6.1 | RICH1 | S.Easo | 10 days | Fri 02-05-17 | Fri 02-05-31 | NA | 111FF |
| 120 | 5.6.2 | RICH2 | A.Papanestis | 20 days | Mon 02-03-04 | Fri 02-03-29 | NA | |
| 121 | 5.7 | CALO | 1 day? | Mon 02-02-25 | Mon 02-02-25 | Mon 02-02-25 | ||
| 122 | 5.7.1 | ECAL | G.Pakhlova | 1 day? | Mon 02-02-25 | Mon 02-02-25 | Mon 02-02-25 | |
| 123 | 5.7.2 | HCAL | A.Berdyugin | 1 day? | Mon 02-02-25 | Mon 02-02-25 | Mon 02-02-25 | |
| 124 | 5.8 | MUON | D.Hutchcroft | 51 days? | Mon 01-12-17 | Mon 02-02-25 | Mon 02-02-25 | |
| 125 | 5.9 | Magnetic field service | 1 day? | Mon 01-12-17 | Mon 01-12-17 | NA | ||
| 126 | 5.10 | Particle swimmer | 10 days | Fri 02-05-17 | Fri 02-05-31 | NA | 112FF,115FF,116FF,117FF,118FF,125FF | |
| 127 | ||||||||
| 128 | 6 | Commission algorithms (new geometry etc.) | 56 days? | Thu 02-03-28 | Thu 02-06-13 | NA | ||
| 129 | 6.1 | L0PuVeto | Nikhef | 1 day? | Fri 02-05-31 | Fri 02-05-31 | NA | 115 |
| 130 | 6.2 | VELO | C.Parkes | 1 day? | Fri 02-05-31 | Fri 02-05-31 | NA | 115,61 |
| 131 | 6.3 | IT | M.Needham | 1 day? | Fri 02-05-31 | Fri 02-05-31 | NA | 116,65 |
| 132 | 6.4 | OT | J.v.Tilburg | 1 day? | Fri 02-05-31 | Fri 02-05-31 | NA | 117,68 |
| 133 | 6.5 | Tracking | 1 day? | Mon 02-06-03 | Mon 02-06-03 | NA | 130,131,132,71 | |
| 134 | 6.6 | RICH | 37 days | Wed 02-04-24 | Thu 02-06-13 | NA | ||
| 135 | 6.6.1 | Tuning to new tracks | G.Wilkinson | 15 days | Wed 02-04-24 | Tue 02-05-14 | NA | 79 |
| 136 | 6.6.2 | Tuning to new geometry | G.Wilkinson | 10 days | Fri 02-05-31 | Thu 02-06-13 | NA | 118,133FF,81 |
| 137 | 6.7 | CALO | V.Belyaev | 1 day? | Thu 02-03-28 | Thu 02-03-28 | NA | 121,84 |
| 138 | 6.8 | MUON | D.Hutchcroft | 1 day? | Wed 02-04-24 | Wed 02-04-24 | NA | 124,87 |
| 139 | ||||||||
| 140 | 7 | Commission OO-DSTs | 33 days | Wed 02-05-01 | Fri 02-06-14 | NA | 108 | |
| 141 | 7.1 | RAW (digi output) | 28 days | Wed 02-05-01 | Fri 02-06-07 | NA | ||
| 142 | 7.1.1 | Finalise content | M.Cattaneo | 5 days | Wed 02-05-01 | Tue 02-05-07 | NA | |
| 143 | 7.1.2 | Commission Brunel Digi | M.Cattaneo | 5 days | Mon 02-06-03 | Fri 02-06-07 | NA | 130,131,132,137,138,142,129 |
| 144 | 7.2 | EOD (reco output) | 33 days | Wed 02-05-01 | Fri 02-06-14 | NA | ||
| 145 | 7.2.1 | Finalise content | M.Cattaneo | 5 days | Wed 02-05-01 | Tue 02-05-07 | NA | |
| 146 | 7.2.2 | Back converters for RICH reco | C.Jones | 10 days | Wed 02-05-01 | Tue 02-05-14 | NA | |
| 147 | 7.2.3 | Test content with physics analysis | G.Corti | 10 days | Wed 02-05-15 | Tue 02-05-28 | NA | 146,145 |
| 148 | 7.2.4 | Commission Brunel Reco | M.Cattaneo | 5 days | Mon 02-06-10 | Fri 02-06-14 | NA | 143,147,128FF |
| 149 | ||||||||
| 150 | 8 | Release Brunel v10r0 | M.Cattaneo | 0 days | Mon 02-06-17 | Mon 02-06-17 | NA | 110,128,140 |