Another important milestone has been achieved on 24th August:

After the successful installation of the RICH 1 seal to VELO the first section of the beam pipe with the VELO exit window has been mounted to the vacuum vessel.

 

Installation of the RICH 1 seal to VELO 14th and 15th August.

 

 

 

 

 

 

 

 

 

Insertion of the wake filed suppressor and the mounting of the first section of the beam pipe to the VELO vessel.