Guidelines to open a work-site
at point 8
for
CERN Staff, External Companies and
Collaborating Institutes
Before starting any work at point 8, several well defined
procedure has to be followed. To avoid any delay of your interventions this
procedure has to launched well in advance; first documents have to be delivered
three weeks prior the start of your work. On this page we will give you
guidelines, links to the requested documents to be filled in and projects that
have already started.
Please read before proceeding:
If possible, please file your PPSPS in
EDMS
-
At the same time you have to fill in an
AOC - OUVERTURE DE CHANTIER
- via EDH. This form has to be filled in only for an outside enterprise;
work done by CERN or Collaboration Institutes
the AOC does not exist yet.
In this form you have to fill in:
-
In addition to the AOC you have to fill in the INTERNAL
TRANSPORT and HANDLING REQUEST in case you require support from the
Transport and Handling personnel (which is need for most projects).
-
Before you finally start the work, a VIC - JOINT INSPECTION
VISIT on site - has to take place. This inspection will focus on subjects
like access, lift means, co-activities and scaffolding. Only after a
positive outcome will you allow to go ahead with your intervention.
SCAFFOLDING_INSPECTION_SHEET.doc
On-going work
sites at the
LHCb, Point 8
|