LHCb Technical Board 7&9 May 2001
DRAFT
Agenda
Monday, 07/05/01
- Discussion of the TDR for the Vertex LocatorT. Ruf
- Comments on RICH 2/M1 interference R. Lindner
- Discussion and TB recommendation on the EDRs for E-Cal and
H-Cal Modules
- Discussion of the TDR for the Muon System B. Schmidt
Wednesday, 09/05/01
- Approval of summary for last TB
- RICH2: TB recommendation on width in z
- IT: Conclusion on the baseline choiceO. Steinkamp
AOB
New results on cross shaped inner tracker M. Merk
Presentation of EDMS in LHCb (postponed) D.
Lacarrere
LHCb milestones up to TDR submission
Participants: G. Carboni, J. Christiansen, H.
Dijkstra, W. Flegel, R. Forty, John Harvey,
H.J. Hilke, B. Hommels, B. Jost, D. Lacarrere, J. Lefrançois,
R. Lindner, M. Merk,
T. Nakada, T. Ruf, B. Schmidt, A.Schopper, O.Steinkamp. I.
Videau,
Excused: (Monday)
O. Schneider, B. Koene, D. Websdale, C. Matteuzzi
- T. Ruf presented the new draft of the TDR for the VELO, pointing out the
changes applied to the first draft and the few missing parts.
The submission of the draft version 3 to the collaboration is foreseen for
May 10th
and the deadline for any comment is proposed to be May 21st. The
final document should be printed May 29th. The TB had a detailed
discussion on the draft, which was generally well received. One major worry
remained, the increased amount of material.
The TB requested that the optimization of the detector layout be
continued after the TDR, with the aim to reduce the radiation thickness. The
TB agreed on the proposed schedule for the TDR submission..
- R. Lindner informed the TB about the conflict in the layout of RICH-2 and
Muon Station 1, caused by the suppression of T11 and the extension of RICH-2
by 330 mm in the downstream direction. The total width of RICH-2 amounts to
+/- 4610 mm in x at present, which restricts the space for the electronic
racks of the first Muon Station (annex 1) and hence the maintenance of the
SPD/PS detector. The RICH and Muon groups expressed their conviction that a
solution could be found.
The TB agreed on the extension of RICH-2 by 330 mm, if the conflict
between RICH-2 and M1 can be solved. RICH-2 will than cover the region
from 9450 mm to 11900 mm in z.
- The Calorimeter Group made a proposal for the steps following their
Engineering Design Reviews (EDRs) for the ECAL and HCAL modules, which had
been sent to the TB. After a short discussion, the TB endorsed the
conclusions of the EDRs and made the following recommendations.
- The purchase of raw materials should start on the basis of these EDRs.
- The construction may start (i.e. contracts may be placed for machining the
mechanical parts) after a Production Readiness Review (PRR) has been carried
out inside the Calorimeter Group confirming the availability of approved
final construction drawings and a detailed definition of quality control
procedures validated on the module-0 construction.
- B. Schmidt presented the changes introduced in the Muon TDR. A detailed
discussion followed, although the TDR was considered to be in excellent
shape. One item was debated extensively, the need for a custom made
synchronization chip, considering the necessary effort.
The TB decided that a review on this subject should be organized
soon, if possible in July 2001.
Comments to the TDR draft 2 should be sent before May and submitted to the
LHCC on the May. The TB agreed on the planning for the TDR, comments to
be sent by May 14th
and submission May 22nd
- O. Steinkamp informed the TB that the Inner Tracker group agreed to the
statement made by the Technical Board in the last meeting (20.4.2001) on the
choice of an all-silicon detector as baseline for the IT.
AOB:
- M. Merk presented studies of a ‘cross-shaped’ Inner Tracker optimized
for maximal 10% occupancy in the Outer Tracker with nominal Luminosity at
LHCb. This results in an Inner Tracker of 500x400 mm2
Å 1400 x 200 mm2
(see Annex 2).
- O. Steinkamp then presented three possible Inner Tracker layouts. A
simple solution consists of four identical modules (220 x 540 mm2) arranged
as a cross around the beam pipe (annex 3). This solution would have many
advantages, but the number of the sensors would increase by 50% compared to
the present design. O. Steinkamp added that further optimization studies are
needed. In view of the Outer Tracker TDR submission in September, B. Hommels
commented that the integration of a ‘cross shaped’ Inner Tracker in the
Outer Tracker has to be clarified. The Outer Tracker Group feels that this
can be arranged relatively easily for stations 7 to 10, but for the stations
in the magnet further investigation are needed.
- No changes to the LHCb milestones (post TDR) were requested.
- Next TB on the 16th July 2001: Outer Tracker TDR